Does anyone know how to filter out/or use any other method to obtain the sequence of activities (logic) preceding a Milestone activity in a P3 schedule.
I have tried to use Longest Path as the selection criteria in the filter, but that gave me only one result for a schedule that has several Milestone activities
Please advise.
I have tried to use Longest Path as the selection criteria in the filter, but that gave me only one result for a schedule that has several Milestone activities