anchorengineer
Structural
- May 26, 2009
- 88
The technical information from scaffold manufacturers gives you the capacity of a frame braced or tied at different tiers (vertically). The majority of scaffoldind designs that I've seen have a horizontal spacing of at least 16' (2 frame bays). Is there technical information to back this up? I don't want to be overly conservative when designing scaffolding but I need to be able to stand behind my work. Is there some horizontal rigidity assumed from adjacent tie bays? Any help is greatly appreciated.
Thanks!
Clarke Engineering Services, PC
Jobsite Engineering and Consulting
Thanks!
Clarke Engineering Services, PC
Jobsite Engineering and Consulting