lovethecold
Civil/Environmental
- Sep 15, 2003
- 97
I am a relatively new geotechnical engineer. The project I am now working on involves giving some recommendations regarding the pavement and subgrade for a rural general aviation airport. The airport would rather be able to rehabilitate the runway if at all possible. The airport was built in the mid to late seventies, since then there has been an overlay placed on the runway. No one is certain of the dates. The overall pavement thickness is approximately 6 to 7 inches. There is noticeable oxidation taking place. While coring, it was noted on several the pavement was raveling. On one core the technician only got through the overlay (1 ½ inches), the rest raveled. The overlay appears to be 1 ½ to 3 inches thick.
The civil working on the airport said that during the summer the runway is relatively smooth with only some cracking. Alligator cracking is negligible. During the winter the runway develops significant heaving. There will be 4 to 6 inch heaves every 4 to 6 feet.
The soil borings show frost to 3 ½ feet. Below the pavement is approximately 1 ½ to 2 inches of sand and gravel base (more in some areas). We are unsure of how much of this is raveled asphalt and actual base material. Fill appears to extend from 1 to 4 feet below grade. The fill is mixed and consists of lean clay with sand, lean clay, and some topsoil. Below the fill the soil is primarily lean clay with sand. About 10 feet the soil is sandy lean clay. The water table appears to be below 11 feet (the depth of our borings). We have been told the water table is at 15 feet.
The moisture density for one of the lean clays was 30% and 90 pcf, at 5 feet (this seems typical of CH soil, not CL soil). Others were higher, but lower than would be expected for lean clays. The way the clay crumbles, it seems like there may be a significant amount of silt mixed in the clay. I am waiting on the Atterberg tests, and am thinking of running a hydrometer.
The runway is generally level with the surrounding ground surface in most areas. In some areas though, the runway is below the surrounding ground surface.
My analysis. Although there is no significant cracking, the pavement is old and has become very porous. As such, there is a fair amount of water seeping to the subgrade. With the runway below the ground level in areas, there is no place for the water to go. I am also thinking the subgrade is not crowned, and is perhaps even concave in some areas, allowing water to pond below. After freeze up, the runway heaves. Although I would expect some heaving, this seems excessive and why I am thinking there is water ponding below the pavement.
It is my opinion the runway and subgrade should be replaced. The subgrade should at minimum be scarified and recompacted, and crowned to allow drainage out from under the pavement. Also, the higher ground surrounding the runway should be cut back and have drainage ditches installed. I am thinking of recommending the subgrade be cut to 3 feet and replaced with non frost susceptible sand (if it is in their budget). The biggest issue will be how the airport has to spend.
Is there something I am missing? What recommendations might you have, are there other questions I should ask? Thank you for any help.