Rounding Problem with Actual Work Column 1

Status
Not open for further replies.

mperr97

Computer
Joined
Dec 25, 2002
Messages
3
Location
US
I added three columns in Microsoft Project 2000:
1.) work
2.) actual work
3.) remaining work

When I place the actual hours worked, Project rounds the numbers. For instance I place 262 actual hours and when I go to the next line, Project takes the 262 and changes it to 262.08. Is there a way to make Project except only what I place in the actual work column so that the remaining hours is correct? Any help is greatly appreciated.
 