msquared48
Structural
- Aug 7, 2007
- 14,745
Have a steel skid mounted 500# rooftop 25 KV generator that needs to set on a 3" concrete isolation slab (roughly 3' X 6") on a 1/4 in 12 sloping roof.
I have done a lot of AC units on the roof, but never a generator with a concrete isolation slab there. Floor, yes, roof no.
Other than any extra structure below the roof sheathing, what is the normal method of installation in a high seismic area considering the slab and new roof penetrations?
Mike McCann
MMC Engineering
Motto: KISS
Motivation: Don't ask
I have done a lot of AC units on the roof, but never a generator with a concrete isolation slab there. Floor, yes, roof no.
Other than any extra structure below the roof sheathing, what is the normal method of installation in a high seismic area considering the slab and new roof penetrations?
Mike McCann
MMC Engineering
Motto: KISS
Motivation: Don't ask