foley7
Civil/Environmental
- Feb 3, 2011
- 6
I posted a thread earlier about overlaying a roadway with 2 inches of asphalt. After the survey was performed the existing roadway profile grade line is not smooth...after reviewing the existing profile grade the general slope of the road is -0.20% with variable grade breaks that are a couple of tenths and hundreths on 50 ft intervals. When preparing the proposed profile grade is it worth making the profile smooth or just follow the existing profile grade? If the profile is smoothed out is it going to be a construction headache that's not worth the effort?