1. Should a risk register for EPC project include hazards?

Thanks for your anticipated feedback
 
Do you have just one risk register? If so, then if the safety hazard is inherent in the project, then it should be included. There are organizations that have separate registers for safety.



TTFN
faq731-376
7ofakss
 
Thanks. - we have one register.
 