kedpe
Civil/Environmental
- Jun 20, 2006
- 25
Hey guys-my first post:
I've designed a fire supply and retention pond and called out 18" deep ODOT Type C (6"-18"; avg. 12") for the pond edges. The contractor wants to put #2 stone.
Any experience?
Thanks
I've designed a fire supply and retention pond and called out 18" deep ODOT Type C (6"-18"; avg. 12") for the pond edges. The contractor wants to put #2 stone.
Any experience?
Thanks