I have a 6' high retaining wall supporting a concrete slab for storage rated at 150psf. The retaining wall will be 8" cmu block fully filled with grout 3000psi. No. 5 vertical bar will be every 8"oc. The wall will be verically braced with timber during the backfill process.
My belief is no compacted backfill should occur until the wall is fully in place, with rebar and fully grouted. I also believe the grout should cure 7 days prior to any backfilling. Your thoughts?
My other question is - with a poured in place concrete retaining wall 6' high - how long should the concrete cure before backfilling is allowed.
Many thanks,
Joel
My belief is no compacted backfill should occur until the wall is fully in place, with rebar and fully grouted. I also believe the grout should cure 7 days prior to any backfilling. Your thoughts?
My other question is - with a poured in place concrete retaining wall 6' high - how long should the concrete cure before backfilling is allowed.