Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Retaining Wall 1

Status
Not open for further replies.

eltelme

Structural
May 6, 2009
4
I need a retaining wall along a sloped ground.So, am I allowed to use stepped footing for the retaining wall.

Another question:

My retaining wall is approximately 100m long, so do I need to provide expansion joints. What is the spacing
 
Replies continue below

Recommended for you

Steps are fine; expansion joints at 30 meter max spacing.

Download a copy of the NYSDOT Bridge Manual. It explains everything.
 
bridgebuster,

I would have thought something considerably less than 30 m for expansion joint spacing, particularly if large daily temperature fluctuations may be expected.

BA
 
you don't need those footings at the steps just underneath the wall.

Regards,
Qshake
[pipe]
Eng-Tips Forums:Real Solutions for Real Problems Really Quick.
 
Dear Qshake,

Thanks for your post, but what do you mean by "just underneath the wall"? Do you mean that the footing can be constructued directly on the slopping ground? but I am afraid in this case of the sliding instability. Would you explain?

Thanks,
 
BA - 30m/90Ft is the maximum spacing for expansion joints. Contraction joints are placed at 10m/30ft intervals.

There could be localized areas in NY with a large daily fluctuation in temperature - Buffalo comes to mind. Most of the projects I've worked on for NYSDOT have been in the NYC area, we've never had a problem with the maximum spacing.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor