SNORGY
Mechanical
- Sep 14, 2005
- 2,510
Client has an existing compressor proposed to be relocated from Site A to Site B (Alberta, Canada). To achieve suitability in the new service, the nameplate pressure needs to be increased from about 4520 kPag @ 149 C to 4960 kPag @ 55 C. An in-service inspection is planned prior to relocation, but the AI's documentation with respect to extent of NDE is disappointingly vague or silent, other than making references to API standards (e.g., 510 - which I have ordered...).
In absence of better data, my plan is as follows:
(1) Thorough in-service visual to verify general condition, confirm nameplate against Manufacturer's Data Reports, etc.
(2) Shut down for internal visual inspection using boroscope as required to look for signs of corrosion / pitting.
(3) UT traverse for 360 degrees of the circumference along entire length of vessels / bottles, 4" (100 mm) spacing for thickness examination.
(4) UT on Category D nozzles.
(5) MPI (external) on circumferential weld seams, with any indications measured against ORIGINAL Edition of Code Of Construction (I don't want to be telling the folks in the field to start chasing out crack indications that, had they been found during original fabrication, would have been accepted).
(6) Re-run vessel design calculations based on measured thicknesses to see if re-rate is acceptable according to CURRENT Edition of Code Of Construction.
(7) Submit application with records and calculations to Jurisdiction for approval.
Any thoughts or suggestions regarding the above? I am kind of flying by the seat of my pants here but, like everything else I am dealing with, it's a schedule crisis...
In absence of better data, my plan is as follows:
(1) Thorough in-service visual to verify general condition, confirm nameplate against Manufacturer's Data Reports, etc.
(2) Shut down for internal visual inspection using boroscope as required to look for signs of corrosion / pitting.
(3) UT traverse for 360 degrees of the circumference along entire length of vessels / bottles, 4" (100 mm) spacing for thickness examination.
(4) UT on Category D nozzles.
(5) MPI (external) on circumferential weld seams, with any indications measured against ORIGINAL Edition of Code Of Construction (I don't want to be telling the folks in the field to start chasing out crack indications that, had they been found during original fabrication, would have been accepted).
(6) Re-run vessel design calculations based on measured thicknesses to see if re-rate is acceptable according to CURRENT Edition of Code Of Construction.
(7) Submit application with records and calculations to Jurisdiction for approval.
Any thoughts or suggestions regarding the above? I am kind of flying by the seat of my pants here but, like everything else I am dealing with, it's a schedule crisis...