LittleInch
Petroleum
- Mar 27, 2013
- 22,761
I've got a peculiar situation which I would appreciate some input / experience.
We have a pretty thin (7.8mm) pipeline with a D/t of about 100, some 40yrs old with some identified corrosion defects under a road crossing.
Fairly uniquely in my experience, we are able to open cut the road to effect repairs as the owner is very reluctant to shut down and clear the pipeline to allow replacement / diversion.
The planned method was to use composite repairs on the multiple locations within the crossing where it requires it with some other non critical defects being subject to coating repair.
The picture is complicated by the pipe previously utilising a concrete sleeve which needs to be broken up to gain access to the pipe. We would like to then simply compact the back fill and do away with the casing or any other protective device (slab/half sleeve etc). According to API 1102, we're at the ragged edge (~0.95 of allowable stress) of acceptance, based on the original nominal wall thickness, even with a reduced MAOP from the original design.
My issues and concerns are:
1) API 1102 does not cover anything to do with defects to the pipe
2) With the number of repair sleeves in a relatively short section, I'm concerned about possible stress concentrations due to the additional loadings from the crossing
3) It is not clear whether composite types repairs, or indeed other repairs as listed in B 31.4, sec 451.6 are valid for crossings
My thoughts have swung towards recommending a single split sleeve with epoxy infill, but would greatly welcome thoughts and experience on the points above.
If you want any more info please ask, but I need to be circumspect in what I can put out there.
Thanks
LI
Remember - More details = better answers
Also: If you get a response it's polite to respond to it.
We have a pretty thin (7.8mm) pipeline with a D/t of about 100, some 40yrs old with some identified corrosion defects under a road crossing.
Fairly uniquely in my experience, we are able to open cut the road to effect repairs as the owner is very reluctant to shut down and clear the pipeline to allow replacement / diversion.
The planned method was to use composite repairs on the multiple locations within the crossing where it requires it with some other non critical defects being subject to coating repair.
The picture is complicated by the pipe previously utilising a concrete sleeve which needs to be broken up to gain access to the pipe. We would like to then simply compact the back fill and do away with the casing or any other protective device (slab/half sleeve etc). According to API 1102, we're at the ragged edge (~0.95 of allowable stress) of acceptance, based on the original nominal wall thickness, even with a reduced MAOP from the original design.
My issues and concerns are:
1) API 1102 does not cover anything to do with defects to the pipe
2) With the number of repair sleeves in a relatively short section, I'm concerned about possible stress concentrations due to the additional loadings from the crossing
3) It is not clear whether composite types repairs, or indeed other repairs as listed in B 31.4, sec 451.6 are valid for crossings
My thoughts have swung towards recommending a single split sleeve with epoxy infill, but would greatly welcome thoughts and experience on the points above.
If you want any more info please ask, but I need to be circumspect in what I can put out there.
Thanks
LI
Remember - More details = better answers
Also: If you get a response it's polite to respond to it.