ozziz
Structural
- Jul 20, 2005
- 46
In a project, it is specficed that all 1200mm dia marine steel tubular piles in 18m deep of water had to be temporary braced and can only be released before installation of the steel roadway frames. All the steel piles are directly socketed into rock and grouted with 40 MPa concrete. There is no other overburden.
The contractor wanted to release the temporary brace to the piles after 3 days when the concrete grout achives 25 MPa.
What do the designer has to check for if the contractor wanted to release the brace at earlier date? Base on the environment loads and strength of the piles, there is no problem as the 1 in 20 years ARI loads are significantly less than 1 in 100 years condition.
The contractor wanted to release the temporary brace to the piles after 3 days when the concrete grout achives 25 MPa.
What do the designer has to check for if the contractor wanted to release the brace at earlier date? Base on the environment loads and strength of the piles, there is no problem as the 1 in 20 years ARI loads are significantly less than 1 in 100 years condition.