chepe35
Marine/Ocean
- Jan 15, 2004
- 3
Hello friends,
as a newbie I try to plan as I ever did (on paper): Define resources (persons), estimate work hours of each sub-task and then - expect to see the duration of the task.
But the program only shows me under "Duration" the longest work time of all the related sub-tasks, but not the added work time of all related sub-tasks.
What do I have to do?
as a newbie I try to plan as I ever did (on paper): Define resources (persons), estimate work hours of each sub-task and then - expect to see the duration of the task.
But the program only shows me under "Duration" the longest work time of all the related sub-tasks, but not the added work time of all related sub-tasks.
What do I have to do?