hondashadow1100vt
Civil/Environmental
- Dec 30, 2008
- 108
I am a PE (mechanical) working on a construction project. Our contractor is in the process of building reinforced concrete equipment bases for tanks, pumps, etc. The reinforcing steel and form work have been completed but concrete has not been placed. The design calls for the top mat of steel in the equipment bases to have 1-1/2" of concrete cover however, as constructed, the contractor has installed the steel to have 3" of concrete cover. I am not a structural engineer but I would like to be armed with a technical understanding of what could happen if the amount of concrete cover over the top mat of steel is not corrected. What are the technical problems that could result from leaving this matter uncorrected?