GalileoG
Structural
- Feb 17, 2007
- 467
I have an existing suspended 12” reinforced concrete ground floor slab (basement below) in an industrial building. This slab will need to support new equipment that will apply a uniform pressure on the floor exceeding the original floor design load of 250psf. These are large equipment with weights exceeding 50,000 lbs.
I am evaluating several options for reinforcing the existing floor. One option is to build a “drop panel” under the existing ground floor with a plan size to match the new equipment. The “drop panel” would be a 12” thick slab supported on steel beams that are supported on steel posts. The steel posts would be supported by micropiles at basement level.
The slab would be tight against the existing slab. There would be ties connecting the existing slab to the new slab and the surface between the two slabs would be roughened and a bonding agent would be applied. The effects of stress redistribution on the existing slab and girders would be considered.
Is this a practical approach to reinforcing the existing floor? What are some constructability issues that may arise? Any alternatives?
I am evaluating several options for reinforcing the existing floor. One option is to build a “drop panel” under the existing ground floor with a plan size to match the new equipment. The “drop panel” would be a 12” thick slab supported on steel beams that are supported on steel posts. The steel posts would be supported by micropiles at basement level.
The slab would be tight against the existing slab. There would be ties connecting the existing slab to the new slab and the surface between the two slabs would be roughened and a bonding agent would be applied. The effects of stress redistribution on the existing slab and girders would be considered.
Is this a practical approach to reinforcing the existing floor? What are some constructability issues that may arise? Any alternatives?