I haven't paid attention to this thread recently, but to respond:
Where required for formwork/falsework provisions, the inserts are specified by the construction engineer here. The folks at the precasting yard install them only. I assume that was what you meant, but I just wanted to be clear. However, due to the regulatory changes we have been seeing, having inserts for formwork installed by the folks at the precasting yard (or anyone else) is not permitted in some locations.
I am curious on what those bracing standards are. I know some DoTs have prescreptive bracing requirements for girders prior to and during the deck pour (eg. things like ties between studs or stirrups at every x distance). When I see these recently, I always wonder how often they are updated, since in the last ten years we have seen overhang widths and deck finisher weights increase dramatically. On type V AASHTO girders and steel girders typical overhangs used to be in the three to four foot range, with the maximum being around five feet. Now we routinely see deck overhangs of eight feet or more. Over the same period of time the typical deck finisher weight has more than doubled (the older finishers were usually pushing 5000lbs an end while we have seen weights up to 15,000lbs an end recently).
At the same time, I have yet to see somewhere with standards that do not say that the designer shall take into account the loads during construction during the design and in every case have seen designs that do not adequately account for the torsion on exterior girders during the deck pour. That is not to say that all or most designers neglect this, but it is a fairly common occurence. In recent years, part of this has been due to the aforementioned increase in deck finisher weight - it's not uncommon for the expected finsher weight to be given on the drawings and nine times out of ten it is low now.
In the places where this is an issue, attaching even single point tie offs to the stirrups is unaccceptable as the stirrups are epoxy coated and doing so could damage the coating.
Everything we do in this regard is regulated by either a state DoT or provincial MoT.
Launching is uncommon, but not rare if you do work outside of urban areas. I average roughly one launch design a year.
The frustrating part is not knowing the reasoning behind the changes, not having any input/conversations with those making the changes and the vast differences between jurisdictions. I have five ongoing construction projects in three different jurisdictions. There are overlapping design firms and design teams between them. In one area the contractors cannot have inserts cast into the girders, cannot Hilti into them or weld to them unless there are problems with the existing diaphragms and cannot leave any steel within the deck that is not specified on the design drawings other than formwork hangers. In the second, the contractors can have inserts into the girders, have the same restrictions on coring and welding and can leave steel in the deck as long as it is glavanized. In the third the contractors can have inserts cast into the girder, can Hilti into the top flange of precast girders, weld extra studs to steel girders and leave extra steel in the deck as long as it meets cover requirements. The bridge designers will and have approved all of these items in each case, it has only been the regulatory body that has said no.