This is regarding query for the stamping requirements of the equipment and piping related to the Reformer package. Components designed as per ASME SEC I ( Waster Heat Boiler coil , steam superheat coil & Steam Drum ) , ASME SEC VIII ( Waste Heat Boiler ) , ASME B31.1 ( Process piping , steam , water piping and cross overs ). Client requirement is all ASME Designed equipment shall be provided with ASME stamps .
Apart from this reformer tubes and process coils designed as per API 530 / ISO 13704. Remaining convection coils , transfer line / collector there is no clear specification .
My question
1. Does piping (ASME 31.1)required stamping.
2. As checked at site WHB Sec VIII , Steam superheat coil Sec I, steam drum Sec I contains stamp . Remaining waste heat boiler coil and convection coil there is no any stamp .
3. Is there any stamping requirement for convection coil and transfer line.
Kindly share valuable inputs .
Thanks and Regards
Abraham ap
This is regarding query for the stamping requirements of the equipment and piping related to the Reformer package. Components designed as per ASME SEC I ( Waster Heat Boiler coil , steam superheat coil & Steam Drum ) , ASME SEC VIII ( Waste Heat Boiler ) , ASME B31.1 ( Process piping , steam , water piping and cross overs ). Client requirement is all ASME Designed equipment shall be provided with ASME stamps .
Apart from this reformer tubes and process coils designed as per API 530 / ISO 13704. Remaining convection coils , transfer line / collector there is no clear specification .
My question
1. Does piping (ASME 31.1)required stamping.
2. As checked at site WHB Sec VIII , Steam superheat coil Sec I, steam drum Sec I contains stamp . Remaining waste heat boiler coil and convection coil there is no any stamp .
3. Is there any stamping requirement for convection coil and transfer line.
Kindly share valuable inputs .