Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Recommended a second hydrotest if PWHT done after first hydrotest?

Status
Not open for further replies.

AWDMIKE

Mechanical
Mar 11, 2006
76
I have a new pressure vessel which is not Code stamped. For process conditions it is required to be PWHT, but this requirement was added after the vessel had been hydrotested. The vessel is still at the shop and will now receive a PWHT.

Is it recommended to perform a second hydrotest after the PWHT is complete? Any responses are appreciated.
 
Replies continue below

Recommended for you

if this was a code vessel, it would have to be hydrotested after the pwht.

Hydrotest is the last thing to be done after all fabrication processes are complete.

but this is not a vessel.

If it were me, i would re hydro and roll the cost into the adder for pwht.
 
Is it recommended to perform a second hydrotest after the PWHT is complete? Any responses are appreciated.

Yes. See Section VIII, Div 1 UG-99.


 
I think a few more details are required as OP states this is not a code vessel and the PWHT is required for process reasons. Granted the second hydro would be preferred approach if it's just a stress relief that is needed for process conditions a lower temperature approach might be the way to go.
 
Assuming that the contract specification required design, fabrication and testing to be done per ASME VIII but stamping was not required due to location of installation, the vessel should be rehydrotested.

 
Thank you for all of the responses. We've decided that the vessel will be re-hydrotested after the PWHT.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor