justinwest
Petroleum
- Aug 17, 2007
- 15
I've been tasked with helping standardize flowlines on natural gas wellsites. No code seems to step up and claim this area in it scope, though B31.8 expressly excludes the lines from the wellhead. The lines will be from Wellhead to Separator to TOC meters.
Our best consensus is B31.3.
Has anyone encountered this delimma, and what was the ultimate decision?
We have also thought to break it down by what line is carrying what i.e., 31.4 for condensate, 31.8 for gas after the separator, 31.3 for the raw gas prior to separation, etc.
This could very well turn into a chaotic mess during construction!
Our best consensus is B31.3.
Has anyone encountered this delimma, and what was the ultimate decision?
We have also thought to break it down by what line is carrying what i.e., 31.4 for condensate, 31.8 for gas after the separator, 31.3 for the raw gas prior to separation, etc.
This could very well turn into a chaotic mess during construction!