PWHT HOLDING TEMP. & TIME 1

Status
Not open for further replies.

sarawana

Mechanical
Joined
Oct 10, 2020
Messages
23
Location
IN
Dears frds,

pls clarify, How to find heat treatment of pwht holding temperature and holding time?
in material sa-516 gr 70(NACE+ HIC)


thanks & best regards,
saravana
 
Rd th Cde :)

The problem with sloppy work is that the supply FAR EXCEEDS the demand
 
HIC + NACE material would require some extra holding temp and time apart from the minimum requirements of the ASME BPVC code. Usually these requirements are given in a client material Specification. Please demand these specs from your client / process licencor/ EPC Contractor.

 
See:
NACE SP0472
NACE 8X194

Regards

 
Or, retain a professional welding engineer

"If you don't have time to do the job right the first time, when are you going to find time to repair it?"
 