RustyTools
Mechanical
- Feb 23, 2005
- 8
When the house was built in 1992, the builder ran a 2' wide spread footing down the center of the basement (70' long) but only made it 6" thick. He located colums about every 6' on this footing. He poured a 4" thick unreenforced slab over the footing and the entire floor. From my calculations the loads on the columns are 2000 to 8000 lbs. I am putting a column between these columns on that same spread footing. It will be bearing 23,000 lbs.
It is too difficult to cut out the existing footing. I am uncomfortable with simply putting 23,000 lbs on that footing. My first choice would be support the column by pouring a reenforced 4' x 4' footing 1' thick on top of the slab. I realize it is kind of big, especially since the soil can support about 3000 psf, but it would cover the hole that was cut to find out what footing were there already. This section of the basement isn't used so the loss of floor space is not a big deal. So now you would have a 4'x4'x1' footing, sitting on top of a 4" slab, sitting centered on a 2' wide x 70' long spread footing.
Another option would be to dig underneath the 2' wide footing, pour a 3' x 4' x 1' thick footing UNDERNEATH the footing and have the 23,000 lbs rest on the old slab. (I would use a 1' x 1' x 1/2" thick steel plate to spread the load) So it would be 1/2" plate, 4" slab, 6" old footing and 1' new footing. This option would leave a level floor but require more work.
In another spot I have a 9000 lb load. I feel comfortable the slab + old 6" footing could take this load.
I have never run into a footing that is only 6" thick. Any thoughts on this matter?
It is too difficult to cut out the existing footing. I am uncomfortable with simply putting 23,000 lbs on that footing. My first choice would be support the column by pouring a reenforced 4' x 4' footing 1' thick on top of the slab. I realize it is kind of big, especially since the soil can support about 3000 psf, but it would cover the hole that was cut to find out what footing were there already. This section of the basement isn't used so the loss of floor space is not a big deal. So now you would have a 4'x4'x1' footing, sitting on top of a 4" slab, sitting centered on a 2' wide x 70' long spread footing.
Another option would be to dig underneath the 2' wide footing, pour a 3' x 4' x 1' thick footing UNDERNEATH the footing and have the 23,000 lbs rest on the old slab. (I would use a 1' x 1' x 1/2" thick steel plate to spread the load) So it would be 1/2" plate, 4" slab, 6" old footing and 1' new footing. This option would leave a level floor but require more work.
In another spot I have a 9000 lb load. I feel comfortable the slab + old 6" footing could take this load.
I have never run into a footing that is only 6" thick. Any thoughts on this matter?