Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Punching shear on rat slab.

Status
Not open for further replies.

tmoe

Civil/Environmental
Mar 3, 2011
33
Hi all,

Im designing a shoring system for a contractor who is cutting floor joists for the work he is doing. There are shoring jacks supporting a second story load (with sleepers to distribute load) which rest just inboard of where he will be making his cut. As a result, I had intended to put 4x4 posts (which he has a bunch of lying around)under the joists to support them. The post would span about 18" to a 2" rat slab below.

Im using equation 55.17 shown here for punching shear stress and Im showing failure.

I thought maybe putting a sleeper under the post, such as a 2X6 or 2x10 would help spread out the load, but I have tried a few options and it appears that changing the area the post is distributed over has little effect on eq. 55.18. The minimum value seems to always end up as 2, and thus gives the same result when plugged into 55.17.

Any ideas on how I can solve this such that punching is ok?
 
Replies continue below

Recommended for you

How much force per post are we talking?
 
I'm from Alberta. We're rat free. Could we call it a mouse slab?

BA
 
BA:
What’s a moose slab? What’s the average area of a moose paw, so I can figure the bearing area?

How thick is the slab, conc. strength, allowable underlying soil bearing pressure, what post size and loading, etc. You certainly should get a higher capacity out of a 4x4 post when it had a 2' long 4x4 under it and atop the slab, than if the post bears directly on the slab. That’s dependent on the bending strength of that horiz. bending member, but it does increase the bearing area. If you have to depend on a cookbook and a specific formula to do this problem, that might be an indication that you should talk this over with your boss and get some local help on this design, for a better understanding of the whole concept.
 
All joking aside, and I did enjoy them, forget trying to get a 2" concrete slab to work structurally, for punching shear or anything else. You will have to provide spreaders/cribbing/temporary footings for the shoring loads on the soil. Neglect the "rat" slab.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor