Lion06
Structural
- Nov 17, 2006
- 4,238
I've been looking for a good detail to temporarily release a PT slab from restraining wall elements that have multiple levels of wall and I'm having no luck. PTI has one detail they call a temporary release for this condition, but I see some issues with it and want something different. I specifically want to allow the slab to continue to shrink while the entire structure is going up and have the voids around the vertical wall bars grouted in at the end. The PTI detail, IMHO, only addresses the elastic shortening of the slab due to prestress and whatever shortening happens prior to the next wall lift being poured. That's not enough, to me, if you have very stiff elements at opposing ends and a pour strip is not an option.
This is specifically for shearwalls, because gravity walls can be a permanent release and then the detail gets a little easier.
With that in mind, an additional question I had is this. Is the bondbreaker critical to the release? If you get a hard trowel finish so there is no aggregate interlock, I would expect the prestress force to exceed the bond strength of the slab to wall interface and allow that movement. This may become problematic as additional floors are built and then the shrinkage may not be able to overcome all of the frictional force. My concern with a bondbreaker is that because of the cold joint, you're required to use shear friction for shear transfer across the joint for the in-plane shear forces. If you reduce the friction to essentially 0, you have no shear friction capacity. ACI 318 states that 0.6 was selected for the coefficient of friction of smooth concrete to smooth concrete to match test results, but that the primary force transfer is through dowel action. Is that reasonable to assume you can use 0.6 (or something close to it) for any interface, regardless of the coefficient of friction between the two surfaces?
I'm developing a detail, but it won't be an inexpensive detail, so I wanted to see if there is anything else out there.
This is specifically for shearwalls, because gravity walls can be a permanent release and then the detail gets a little easier.
With that in mind, an additional question I had is this. Is the bondbreaker critical to the release? If you get a hard trowel finish so there is no aggregate interlock, I would expect the prestress force to exceed the bond strength of the slab to wall interface and allow that movement. This may become problematic as additional floors are built and then the shrinkage may not be able to overcome all of the frictional force. My concern with a bondbreaker is that because of the cold joint, you're required to use shear friction for shear transfer across the joint for the in-plane shear forces. If you reduce the friction to essentially 0, you have no shear friction capacity. ACI 318 states that 0.6 was selected for the coefficient of friction of smooth concrete to smooth concrete to match test results, but that the primary force transfer is through dowel action. Is that reasonable to assume you can use 0.6 (or something close to it) for any interface, regardless of the coefficient of friction between the two surfaces?
I'm developing a detail, but it won't be an inexpensive detail, so I wanted to see if there is anything else out there.