ExQAMan
Computer
- Mar 20, 2006
- 4
I would like Duration to automatically calculate based on Work and Resources. Project seems to work fine, when using one resource, but using multiple resources, the Duration calculation appears to be off. As an example, I will create a task for 10d (80hrs), and add two resources (one full-time and one part-time), at 75% each (9hrs/day combined). I would assume the Duration would calculate to 8.88d(80hrs/9hrs) and an End Date of 4/20/06 (if started on 4/10/06), but it instead calculates to 9.92d. Not only that, but the End Date is calculated to 4/28/06 (which is 15 business days long). What am I missing?