Hello,
I am in the process of integrating a project schedule into another main schedule. One task was for 5 days - 11/7 to 11/13. When I pasted the plan into the main schedule it changed to 5 days 11/7 to 11/14. The calendar is the same for both (standard working time). Has anyone ever seen this before? If so, do you know what causes this to happen and how to fix it?

Thanks!
 
You need to change the display settings to show the time during the day and follow your schedule. When you integrate schedules, you change the dependencies, so you need to examine the predecessors of each task.

TTFN