Stazz
Structural
- Oct 22, 2008
- 100
I just wanted to get some input in how you guys tweek the Baseplate - Tie Rod interaction on these buildings:
I have 135' clear span pre-engineered frame with a 30' foot trib and the outward kick on this needs some tie rods.
I designed the tie rods for strength first and then I went WOOOOOAAAAA, these suckers are going to elongate a lot.
Then I designed for the deflection and I went HEEEEEEEY! This is a lot of freeking steel.
Then I looked at previous jobs and saw that the documents made a note telling the contractor to tension the Tie Rods to produce a net lateral displacement at the baseplate and I went PHE Now I can design for just the live load deflections.
The note says to tighten after all purlins, frames and decking are erected until each baseplate deflects 3/16 of an inch. But wouldn't it be better to specify a tension force? because what if the baseplates don't even kick out under the dead load as anticipated if the grout-baseplate interaction is extra strong that day (then your pulling extra hard and overcompensating). Or does this grout going to act more like butter compared to the kick force making the supports more like a pin-roller at first?
Also, do you guys make them wait until all of that dead load is on (purlins and deck)? Or just the bare frame dead load. Don't they have to tighten the rods before the slab gets poured? then how do they pour the slab when the roof is on the building? These construction documents might be a bust.
What do the professionals do?
I have 135' clear span pre-engineered frame with a 30' foot trib and the outward kick on this needs some tie rods.
I designed the tie rods for strength first and then I went WOOOOOAAAAA, these suckers are going to elongate a lot.
Then I designed for the deflection and I went HEEEEEEEY! This is a lot of freeking steel.
Then I looked at previous jobs and saw that the documents made a note telling the contractor to tension the Tie Rods to produce a net lateral displacement at the baseplate and I went PHE Now I can design for just the live load deflections.
The note says to tighten after all purlins, frames and decking are erected until each baseplate deflects 3/16 of an inch. But wouldn't it be better to specify a tension force? because what if the baseplates don't even kick out under the dead load as anticipated if the grout-baseplate interaction is extra strong that day (then your pulling extra hard and overcompensating). Or does this grout going to act more like butter compared to the kick force making the supports more like a pin-roller at first?
Also, do you guys make them wait until all of that dead load is on (purlins and deck)? Or just the bare frame dead load. Don't they have to tighten the rods before the slab gets poured? then how do they pour the slab when the roof is on the building? These construction documents might be a bust.
What do the professionals do?