txdilbert
Mechanical
- Apr 3, 2008
- 15
Guys,
Have a customer that wants to erect an 80' x 60' x 20' pre-engineered metal building on an existing 100' x 100' monolithic concrete slab to control cost. Core samples suggest the slab was poured at 12" thick(?), with no reinforcement. Unclear what type of concrete mix was used.
Since the customer is adamant about avoiding unnecessary site work, a cost engineered solution is in order. I'd definately like to hear how folks on this site might approach this project. Suggestions?
Have a customer that wants to erect an 80' x 60' x 20' pre-engineered metal building on an existing 100' x 100' monolithic concrete slab to control cost. Core samples suggest the slab was poured at 12" thick(?), with no reinforcement. Unclear what type of concrete mix was used.
Since the customer is adamant about avoiding unnecessary site work, a cost engineered solution is in order. I'd definately like to hear how folks on this site might approach this project. Suggestions?