Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Post-tension tendons cut before measuring

Status
Not open for further replies.

Eldorado

Structural
Dec 16, 2003
53
I almost had a project (Slab on grade) that had post tension cable ends cut off before the elongations were measured. It turns out that it was someone elses project, but it made me ask myself how I would be able to verify stressing if there were no elongation data. No data is unacceptable, but I don't want to damage work that is potentially good. Do I have the short cable tails coupled and lift the wedges out to verify tendon stress? What alternate means of verification, if any, might I rely on.
 
Replies continue below

Recommended for you

Your suggestion of lifting the wedges is the only method available so far as I know.

BA
 
Thanks BA. I don't see any other choice as well, but I can't tell you how many times I have issued a fix for a marginal condition only to show up and find things worse than before the fix. This is mostly true when there is a torch around on a steel job, but the idea is the same. Thanks for the input.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor