CEmonkee
Structural
- Mar 8, 2008
- 111
Hi - I'm working on a retrofit. The owner is knocking out a bearing wall and replacing it with a beam and posts to support the overhead floor joists.
The floor below is a concrete slab, 4" to 6" thick. The load to each post is about 2400#. If the slab is 6" thick, I can show it good to support the load, and I was thinking of just attaching the post to the slab with a Simpson post base. Would that be an acceptable solution? Or should I have the slab cut up at that location and have a footing poured for the column? If it's 4" I can't show it good and would have a footing poured in that case.
Thanks for your input!
The floor below is a concrete slab, 4" to 6" thick. The load to each post is about 2400#. If the slab is 6" thick, I can show it good to support the load, and I was thinking of just attaching the post to the slab with a Simpson post base. Would that be an acceptable solution? Or should I have the slab cut up at that location and have a footing poured for the column? If it's 4" I can't show it good and would have a footing poured in that case.
Thanks for your input!