SUGARCANE
Geotechnical
- May 2, 2003
- 10
As a test house in the UK we frequently conduct plate loading tests. The method essentially being based on the requirements of BS 1377: Part 9, ensuring that the plate is loaded such that the settlement recorded is in excess of 1.25mm. We then evaluate the data in accordance with Dpt. Transport Design Manual HD25/94 which gives us the following data:
1. Modulus of Subgrade Reaction (K762) in kN/m2/mm
2. An equivalent CBR Value
3. Elastic Modulus E
This is not always sufficient for our clients (generally earthworks contractors). We are continually being asked (particularly for building platforms as appose to road construction) if we can tell from the results if they have complied with their specification requirements and acheived a specified bearing capacity (generally 75-150kN/m2 dependant on site use).
THIS IS WHERE WE GET STUCK.
The loads that we apply to the plate vary dependant on how competant the soil is that we are testing. In general, we would be putting loads upto 250kN/m2. What we generally tell our clients is that we can interpolate from the load/ settlement graph a settlement at any given bearing pressure applied to the plate and that somebody somewhere (generally the design consultant) should know if this is acceptable.
Can anybody please help. Is there anyway we can determine if our Clients have acheived their contractual requirements.
Keep it simple. We are not all geotechnical engineers!. Nonetheless, we get a hell of a lot of queries from you guys so its not only us that struggles to find the answers.Remember, its supposed to be us that does the testing, you to do the clever stuff.
Anyway, a worked example would be good.
Heres hoping
1. Modulus of Subgrade Reaction (K762) in kN/m2/mm
2. An equivalent CBR Value
3. Elastic Modulus E
This is not always sufficient for our clients (generally earthworks contractors). We are continually being asked (particularly for building platforms as appose to road construction) if we can tell from the results if they have complied with their specification requirements and acheived a specified bearing capacity (generally 75-150kN/m2 dependant on site use).
THIS IS WHERE WE GET STUCK.
The loads that we apply to the plate vary dependant on how competant the soil is that we are testing. In general, we would be putting loads upto 250kN/m2. What we generally tell our clients is that we can interpolate from the load/ settlement graph a settlement at any given bearing pressure applied to the plate and that somebody somewhere (generally the design consultant) should know if this is acceptable.
Can anybody please help. Is there anyway we can determine if our Clients have acheived their contractual requirements.
Keep it simple. We are not all geotechnical engineers!. Nonetheless, we get a hell of a lot of queries from you guys so its not only us that struggles to find the answers.Remember, its supposed to be us that does the testing, you to do the clever stuff.
Anyway, a worked example would be good.
Heres hoping