Lahad Datu Port in Sabah, Malaysia
Consultants were Posford Duvivier
Main Contractor was Kawasaki Steel (project manager Myoshi, assistant Ichise ) . Posfords (for Sabah Port Authority) argued that the increase in pile length (by about 5-10 metres for 390 piles) was the contractor's problem, Kawasaki proved otherwise, after a major investigation effort including British experts. I don't know if the results of arbitration was ever made public, probably some confidentiality clause.
The general principle appears to be that you cannot contract out risk.
Cheers