WARose
Structural
- Mar 17, 2011
- 5,594
I've got a object (a pre-cast, reinforced concrete frame/box combo) where the center of gravity is way off-center. Nowhere near the points where you'd think they would attach for lifting. How do I go about this? Maybe lift with a spreader beam (as opposed to the slings coming to a single point)? The object is about 60' x 26' in plan view.