Here's a new one for the books:
I've been asked to propose on design and construction services for a 40,000+ SF PEMB that was originally manufactured for a location and end use that are different from that required by the present owner. The components are crated up on the new site and need a foundation and cladding.
Other than determining if the structure will work for the environmental loads at the new location and if the maximum drift will be compatible with the new use, what other considerations (or cautions) would you have with this?
Any and all advice would be greatly appreciated.
-Jack
I've been asked to propose on design and construction services for a 40,000+ SF PEMB that was originally manufactured for a location and end use that are different from that required by the present owner. The components are crated up on the new site and need a foundation and cladding.
Other than determining if the structure will work for the environmental loads at the new location and if the maximum drift will be compatible with the new use, what other considerations (or cautions) would you have with this?
Any and all advice would be greatly appreciated.
-Jack