Lion06
Structural
- Nov 17, 2006
- 4,238
I have a situation where the stair guy is attaching a stringer to a bent plate at edge of slab where the slab is cantilevered out past the beam 1'-6".
This was not the intent of the original design and the slab isn't poured yet. I am detailing some rebar in the top of the slab(attached to the bent plate at edge of slab) to take this moment back into the slab.
I can't get a fillet weld around a #4 bar to develop the bar unless it is like a 1/2" weld (that's not going to work). I ended up counting on the length I have from edge of bent plate to centerline of beam (1'-6") to partially develop the rebar and am only counting on the weld to the bent plate for the remaining portion.
Does anyone see any problem with this?
This was not the intent of the original design and the slab isn't poured yet. I am detailing some rebar in the top of the slab(attached to the bent plate at edge of slab) to take this moment back into the slab.
I can't get a fillet weld around a #4 bar to develop the bar unless it is like a 1/2" weld (that's not going to work). I ended up counting on the length I have from edge of bent plate to centerline of beam (1'-6") to partially develop the rebar and am only counting on the weld to the bent plate for the remaining portion.
Does anyone see any problem with this?