New landfill gas generating site with a unit substation (15kV-480V) installed on a containment pad. There is grating from the top inside of dike wall to equipment pad. Edge of pad extends 1'-6" from front and rear doors of 15kv gear. So as you approch the front and rear of the gear you are met with a 6" curb. Is this a violation of the NEC since there is not 3' of level working space at front and rear access doors?
Thanks for your input.