jcbg
Computer
- Mar 15, 2006
- 1
Hi there,
I need to change the start date for an actual date, but I need to keep track of this change. Is there any way to save the original dates and be able to pull it out at any time?
I was thinking about customizing a column and change the header to "Original Date". Can I do this in MS Project.
Is there any other simple way to do this?
Thank you in advance,
JCBG
I need to change the start date for an actual date, but I need to keep track of this change. Is there any way to save the original dates and be able to pull it out at any time?
I was thinking about customizing a column and change the header to "Original Date". Can I do this in MS Project.
Is there any other simple way to do this?
Thank you in advance,
JCBG