Ariel26th
Petroleum
- Sep 4, 2013
- 3
Hi Everyone….
I have several issues regarding a kind of structures that I should design in an environment described below
For introductions, my company currently still in the Conceptual Offshore Oil and Gas Development in Asia, The reservoir that we have lies below mud flats and Peninsula that I should say very Challenging in term of Execution to build Structure/Platform on the land since there are no access to the area from the land (Mangrove area), if we would have to do it from offshore it cannot be far from the reservoir target (Drill Cost!) so we have to build them around the area near the target or I should say mud flats ranging from 2 to 4 meter water depth.
1. Soil analysis indicates that dredging will be ineffective due to the lack of cohesiveness of the soil.
a. Extremely Soft soil until 100’ of soil depth(Soft Clay > 80% water) based on soil survey
b. Stiff Clay only exist beyond 100’ (Stiff Clay < 50% water)
2. Dredging would be required for installation Vessel access of the structures and Drilling Rig access (Swamp Drill Barge operates minimum 5 meters)
a. I guess based on soil survey above dredging nearly impossible
b. Possibility of using sheet pile around to coffer dam the area and use Suction dredging
3. Soil improvement to support the drill rig position when it grounded down
a. We try to use pile and compacted soils and sand bags
I have another thread submitted in soil subject to resolve the issue above, but in terms of structures type below are the problems.
If we would have to build conventional Monopod Structures platform the soils may not have a sufficient strength to support the structures, it might have to be developed in tripod or 4 legged jacket.
a. But how do we install in the structures in this very shallow water if we have to use heavy Crane barge that usually have draft more than 5 meters and for operational we have to have access all the time for drilling rig and operational boat
b. If we have to do dredging first to get the access the issues still lies on the possibility of dredging the soft clay on 80% water content.
c. We try to design in situ shallow structure to avoid using heavy lift crane barge, but this will have huge Offshore Spread Cost instead of pre-fabricated in a fabrication yard
Sorry for the long intro and thanks for your insight….
I have several issues regarding a kind of structures that I should design in an environment described below
For introductions, my company currently still in the Conceptual Offshore Oil and Gas Development in Asia, The reservoir that we have lies below mud flats and Peninsula that I should say very Challenging in term of Execution to build Structure/Platform on the land since there are no access to the area from the land (Mangrove area), if we would have to do it from offshore it cannot be far from the reservoir target (Drill Cost!) so we have to build them around the area near the target or I should say mud flats ranging from 2 to 4 meter water depth.
1. Soil analysis indicates that dredging will be ineffective due to the lack of cohesiveness of the soil.
a. Extremely Soft soil until 100’ of soil depth(Soft Clay > 80% water) based on soil survey
b. Stiff Clay only exist beyond 100’ (Stiff Clay < 50% water)
2. Dredging would be required for installation Vessel access of the structures and Drilling Rig access (Swamp Drill Barge operates minimum 5 meters)
a. I guess based on soil survey above dredging nearly impossible
b. Possibility of using sheet pile around to coffer dam the area and use Suction dredging
3. Soil improvement to support the drill rig position when it grounded down
a. We try to use pile and compacted soils and sand bags
I have another thread submitted in soil subject to resolve the issue above, but in terms of structures type below are the problems.
If we would have to build conventional Monopod Structures platform the soils may not have a sufficient strength to support the structures, it might have to be developed in tripod or 4 legged jacket.
a. But how do we install in the structures in this very shallow water if we have to use heavy Crane barge that usually have draft more than 5 meters and for operational we have to have access all the time for drilling rig and operational boat
b. If we have to do dredging first to get the access the issues still lies on the possibility of dredging the soft clay on 80% water content.
c. We try to design in situ shallow structure to avoid using heavy lift crane barge, but this will have huge Offshore Spread Cost instead of pre-fabricated in a fabrication yard
Sorry for the long intro and thanks for your insight….