I'm working on a revision to a dean's office at a local campus. The main air handler is a CV unit with no excess capacity. The new office layout will require additional cooling airflow than originally designed. What are my options to improve this situation? A fan-powered box would draw warm air from the plenum and probably not help with cooling. An inline booster fan may work, but would 'steal' supply air from other branches on the main duct. Any ideas on other options?
Thanks in advance.