Hello,
We have a new water injection plant that has pipes (above and under ground), above ground tanks, filters and other vessels.
The pre-commissioning and commissioning of the plant were delayed due to some problems with the Contractor.
After long negotiations with the Contractor, they refused to finish their work as they were facing financial and other problems and the contract was terminated by consent
Almost ten years had lapsed now and my Company finally decided to operate the plant by the local resources now.
I wonder if the pipes and equipment have to be subjected to full inspection or can we just make quick checks before the start-up?
Does anyone know any standard or code reference for such situation?
Thanks and best regards,
Ibrahim ALKANSHI
We have a new water injection plant that has pipes (above and under ground), above ground tanks, filters and other vessels.
The pre-commissioning and commissioning of the plant were delayed due to some problems with the Contractor.
After long negotiations with the Contractor, they refused to finish their work as they were facing financial and other problems and the contract was terminated by consent
Almost ten years had lapsed now and my Company finally decided to operate the plant by the local resources now.
I wonder if the pipes and equipment have to be subjected to full inspection or can we just make quick checks before the start-up?
Does anyone know any standard or code reference for such situation?
Thanks and best regards,
Ibrahim ALKANSHI