Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

MS Project Copy Task Information

Status
Not open for further replies.

fish01

Automotive
Aug 25, 2004
1
We have a project that repeats tasks in cycles. We are trying to copy section 1 so that we don't have to re-enter all of the information, then just change the final launch date so that all the other dates change in section 2. We want to keep all of the links and lag information, but when we copy it seems that the link information does not copy the lag correctly if it lies outside a grouping. Does anyone know why this is or how to correct?
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor