redtag2010
Electrical
- Feb 17, 2010
- 2
I'm rebuilding my block foundation walls. I am doing this in sections. I shored up about a quarter of the two story house and took down the block wall and rebuilt them on the existing footing. Walls are 7 feet tall and I used type S mortar and filled every other cell with rebar and grout. Wondering how long before I can set the house back on this portion of the foundation and move onto the next section. Temperatures have been lows in 30's and high's in 50's.