Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Modified Rational Method

Status
Not open for further replies.

salhu

Civil/Environmental
Joined
Jul 22, 2004
Messages
11
Location
CA
Can anybody tell me the difference between Rational and Modified Rational method. Lot of engineers use modified Rational Method for detention volume calcuations, is this an acceptable practice?

Thank you in advance...
 
Here's where the hydrology purists and engineers who have to design things butt heads.

Rational does not give a volume of runoff (cf), only a peak rate (cfs). The Modified Rational allows for construction of a volumetric hydrograph using the Rational peak rate, Tc and storm duration...rate as a function of time, volume as the integral.

Hydrology purists usually reject this method as a rough guess based on incorrect data, and technically, they are right. Engineers, at least in my experience, largely accept this method as valid and conservative enough for small, largely homogenous (parking lots, grass fields) watersheds. I have used Mod. Rational, I actually prefer it in those situations. I have reviewed and approved plans based on calculations from it.

I hope that answer was not TOO evasive...