Hello everyone,
I'm working on 150 kV project that nearly finish. My friend told me that before we 'energize' (the first time that the line powered with 150 kV) the line, we need to megger it. Then it give me some question :
1. is it really necessary? after all, we had have visualy line check to make sure that there were no things that attached on the wire that will cause a short circuited to ground. And the distance of the TL are 40 KM. ain't that ineffective?
2. on the substation, the line were connected to surge arrester. were that okay to do the megger without releasing the connection?
3. are there any international procedure for it (IEC, NETA, etc..)?
thanks..
I'm working on 150 kV project that nearly finish. My friend told me that before we 'energize' (the first time that the line powered with 150 kV) the line, we need to megger it. Then it give me some question :
1. is it really necessary? after all, we had have visualy line check to make sure that there were no things that attached on the wire that will cause a short circuited to ground. And the distance of the TL are 40 KM. ain't that ineffective?
2. on the substation, the line were connected to surge arrester. were that okay to do the megger without releasing the connection?
3. are there any international procedure for it (IEC, NETA, etc..)?
thanks..