There is an existing opening in an existing large CMU wall (its a theatre classroom). The lintel I am assuming is designed to carry the arch of CMUs above. This opening leads to a small foyer and the main door into the theatre.
Now, they want to expand the foyer by removing the rest of the CMU wall to one side of the opening (Its about 7' to the corner of the wall). There will be a concrete post and a concrete lintel installed to carry the load of the removed wall.
So, now that the wall on one side of the opening has been removed does that have an effect on the masonry arch above the existing lintel? Has the loading on that lintel changed? And should the new post and lintel be design to take the thrust?
Thanks again for your help.
I do have one more question:
There is an existing opening in an existing large CMU wall (its a theatre classroom). The lintel I am assuming is designed to carry the arch of CMUs above. This opening leads to a small foyer and the main door into the theatre.
Now, they want to expand the foyer by removing the rest of the CMU wall to one side of the opening (Its about 7' to the corner of the wall). There will be a concrete post and a concrete lintel installed to carry the load of the removed wall.
So, now that the wall on one side of the opening has been removed does that have an effect on the masonry arch above the existing lintel? Has the loading on that lintel changed? And should the new post and lintel be design to take the thrust?
Thanks again for your help.