StoneCold
Chemical
- Mar 11, 2003
- 992
I work in a small chemical plant in the US. Our piping falls under B31.3 for almost everything. Our larger recent projects are handled by contractors who do the welding and we have 5% x-rayed and if there is no problems then hydro and put into service. My question has to do with welding by our maintenance personnel for smaller projects. What is required to be able to use them on small projects? I believe we need to create weld procedures, and have the maintenance guys tested on them. But then it is a little fuzzy for me. Would we need to x-ray 5% of the piping for a small project or just hydro? What if the project only had 4 welds? Should we x-ray 5% of the welds for that welder per year, since they continue to work for us on small projects? I want to get compliant but contracting every weld is very cost prohibitive. Our guys are probably capable of passing the x-ray test on most things that get done. What are all of you doing?
Thanks
StoneCold
Thanks
StoneCold