Should we continue to load bank test the emergency generators in our office buildings at 100% of name plate rating (per NFPA 110) even though the building's emergency power systems connected to the generator represent less than 80% of the generator's name plate rating. We understand the importance of eliminating wet-stacking but it seems wasteful - from an emissions aspect.
Why not load bank (for 2 hours annually) at 80% of rating?