bookowski
Structural
- Aug 29, 2010
- 983
There is a geotech on board for this project but I'd like to have a better understanding of what's going on here and what to expect:
This is a project where we will are doing a substantial vertical enlargement on an existing 6 story building. The enlargement is such that we are adding new foundations (and new columns) but preserving the envelope and some floors etc. Original building is early 1900's. After cutting through the basement slab on grade for test pits water immediately filled the pits (and slab had very thick membrane below).
Borings have shown that soil is subject to liquefaction. We have a report from a few years back for a job only a few doors down and that report showed similar results, i.e. potential for liquefaction.
The building enlargement has triggered a seismic upgrade to the building (original bldg has no distinct/designed lateral system).
I am new to the liquefaction issue, some questions:
- All of the foundation work will be in an existing cellar, maybe 9ft. clear head room. Piles would be tricky.
- From what I've found online compaction grouting sounds like a potential solution for limited access sites. When doing compaction grouting who specifies the process/performance and how is it verified?
- When compaction grouting how is the site classified (for seimsic site class A, B, C etc.)
- How is the bearing capacity determined after grouting?
This is a project where we will are doing a substantial vertical enlargement on an existing 6 story building. The enlargement is such that we are adding new foundations (and new columns) but preserving the envelope and some floors etc. Original building is early 1900's. After cutting through the basement slab on grade for test pits water immediately filled the pits (and slab had very thick membrane below).
Borings have shown that soil is subject to liquefaction. We have a report from a few years back for a job only a few doors down and that report showed similar results, i.e. potential for liquefaction.
The building enlargement has triggered a seismic upgrade to the building (original bldg has no distinct/designed lateral system).
I am new to the liquefaction issue, some questions:
- All of the foundation work will be in an existing cellar, maybe 9ft. clear head room. Piles would be tricky.
- From what I've found online compaction grouting sounds like a potential solution for limited access sites. When doing compaction grouting who specifies the process/performance and how is it verified?
- When compaction grouting how is the site classified (for seimsic site class A, B, C etc.)
- How is the bearing capacity determined after grouting?