nirlt
Mechanical
- Apr 14, 2007
- 14
I would like to know following for Liq. Sulfur Transfer Pumps in parallel operation:
1. If three pumps in liquid sulfur service with PT of 130 Deg.C and Sp. Gr. @ PT as 1.5 gm/cc, are working in 2W+1S configuration taking suction from a common header (not sump) from an atmospheric pressure tank, and delivering to a common header having a PCV. Do you feel pump(s) can really get into a operating situation of End Of Curve(EOC) Flow for prolonged time and not for just few seconds during start up ?
If response is 'Yes', what are those situations may be ?
2. In above mentioned configuration of pumps how critical it would be to ensure a positive margin of say 1 meter of liq. sulfur column between NPSHA and NPSHR throughout operating range of Min. Cont. Flow (MCF) to EOC Flow ?
3. In the process of ensuring a min. margin of 1 mlc of liq. sulfur should we compare NPSHR values at different operating points like MCF, rated Point & EOC with NPSHA at rated Points or we should compare NPSHA value at MCF, Rated Point and EOC respectively ? What is industry practice on this aspect ?
1. If three pumps in liquid sulfur service with PT of 130 Deg.C and Sp. Gr. @ PT as 1.5 gm/cc, are working in 2W+1S configuration taking suction from a common header (not sump) from an atmospheric pressure tank, and delivering to a common header having a PCV. Do you feel pump(s) can really get into a operating situation of End Of Curve(EOC) Flow for prolonged time and not for just few seconds during start up ?
If response is 'Yes', what are those situations may be ?
2. In above mentioned configuration of pumps how critical it would be to ensure a positive margin of say 1 meter of liq. sulfur column between NPSHA and NPSHR throughout operating range of Min. Cont. Flow (MCF) to EOC Flow ?
3. In the process of ensuring a min. margin of 1 mlc of liq. sulfur should we compare NPSHR values at different operating points like MCF, rated Point & EOC with NPSHA at rated Points or we should compare NPSHA value at MCF, Rated Point and EOC respectively ? What is industry practice on this aspect ?