Dear all,
I have to prepare a material take off for line pipe to be used offshore.
My question is regarding spare quantities: is there any standard, guidelines or recomended practice I could use to estimates occurency of wet buckle, spare for welding qualifications, damage due to pipe handling... ?
Thank you